Understanding Report Templates Chapter 5
Rockwell Automation Publication RPTEXP-UM001H-EN-P-June 2014 61
The fields of the report template grid:
Item Description
Uptime % The percentage of available time that the machine was actually
running. The calculation for this field is:
Uptime % = RunningTime/AvailableTime.
Throughput % The performance of a machine when it is running compared to its
ideal cycle time. The ideal cycle time depends upon the product
being produced and is measured in units of seconds per part. The
calculation for this field is:
Throughput = (TotalParts x IdealCycleTime) / Running Time.
Quality % The percentage of total parts produced that were of good quality.
The calculation for this field is:
Quality % = GoodParts / Total Parts.
OEE % The product of Uptime, Throughput, and Quality. The calculation for
this field is:
OEE % = Uptime x Throughput x Quality.
Available Time It may be defined by a schedule or by information from the control
system. Available time may be impacted by scheduled unavailable
time and by the use of Monitored Availability in the work cell's
configuration.
Downtime The amount of time the machine was available, but was not
running. The calculation for this field is:
DownTime = AvailableTime - RunningTime.
Running Time The number of seconds the machine was in a running state.
Good Parts The number of good parts produced.
Scrap Parts The number of parts rejected due to poor quality.
Total Parts The total number of parts produced.
Ideal Parts The total number of parts that could have been produced in the
available time. The calculation for this field is:
IdealParts = AvailableTime / IdealCycleTime.
Scheduled
Unavailable Time
The scheduled unavailable time as defined by the work cell
schedule.
Faults The number of fault states.
TEEP (Total Effective Equipment Productivity (or Total Capacity).) A Key
Performance Indicator (KPI) that is similar to the OEE calculation,
but it uses Total Time instead of Available Time in the calculation:
TEEP = (Good Parts * Ideal Cycle Time)/Total Time
TEEP = OEE*(Available Time/Total Time).