6 USING FACTORYTALK SCHEDULER
85
• • • • •
A section of the Scheduled Orders report showing the orders due on 2/11/03 is shown
below. In the actual report, several different colors are used for the values in the
completion date column. This allows the user to identify easily the late, on-time, and early
orders.
A section of a typical dispatch or work-to list for the Assembly and Pack Area 1 resource
shows the orders scheduled for 2/13/03. The remainder of this report provides a list of
operations scheduled, by day, at each resource in the system.
The Material Level report provides information on the replenishment and depletion of
each of the defined materials. The information for the SHP Frame material is shown
below.